Should We Open a New Distribution Hub? A Full Analytics Framework

Statistics & ExperimentsModel answer
HardModel answerStatistics & Experimentsdemand-forecastingfinancial-modelingexperimentation

Last updated

Design an end-to-end analytical case for a warehouse build-vs-lease decision: demand forecasting, NPV modeling, incrementality experiments, sensitivity analysis, and a stakeholder recommendation.

Opening a New Distribution Hub: Build, Lease, or Wait?

Your team has been asked to evaluate whether the company should open a new distribution hub in an underserved region. Leadership wants a data-driven recommendation before committing capital.

You have access to the following data:

  • Daily order volume broken down by metro area
  • Current hub locations, their storage capacities, and per-hub variable fulfillment costs
  • A delivery-time-vs-distance curve derived from historical shipments
  • Two site options: a build-to-own (large upfront capital) and a short-term lease (lower commitment, higher ongoing cost)

Answer all five parts below.

Part 1 — Analysis Plan Outline the full analytical workflow you would follow to arrive at a build / lease / defer recommendation. Cover: the forecasting methodology you would use for regional demand, the service-level target you would optimize against, the network optimization problem formulation (objective function, decision variables, and key constraints), and how you would isolate the value that a new hub adds versus the current network.

Part 2 — Five-Year NPV Model Walk through a back-of-the-envelope NPV calculation over a five-year horizon with a 10% discount rate. State your assumptions explicitly (rerouted volume, cost savings per unit, demand lift from faster delivery, cannibalization, contribution margin, annual growth, ramp curve, fixed site operating cost). Produce a year-by-year cash-flow table and a final NPV for each option. Call out the key insight about which inputs actually swing the decision.

Part 3 — Pre-Commitment Experiment You cannot A/B test a physical building. Describe two complementary approaches that would let you de-risk the decision before signing anything. For each, explain what it measures, how you would validate it, what your primary and guardrail metrics are, and what your stopping rules look like.

Part 4 — Sensitivity Analysis Identify the three input parameters that pose the greatest threat to the recommendation. For each: quantify how much it can move the NPV, explain how you would bound your uncertainty with additional data, and describe how you would present the results to a non-technical audience.

Part 5 — Stakeholder Narrative Sketch the structure of a single-slide recommendation. Include your headline decision, the one-line rationale for the preferred option over the others, and the top two risks with a mitigation for each.

Hints

Hint 1

For the network optimization, think about it as a facility-location MILP: binary open/close decisions for each candidate site, continuous flow variables between sites and metros, and a hard constraint on next-day coverage percentage. The value of a new site is the difference in total cost with and without it in the feasible set.

Hint 2

In the NPV model, separate cost savings (which are high-confidence and drive the bulk of value) from demand lift due to faster delivery (which is uncertain and much smaller). Notice which option's NPV is positive even if you zero out the demand-lift term entirely — that asymmetry should drive your recommendation.

Hint 3

You can't randomize who gets a new warehouse, but you can simulate the counterfactual two ways: replay historical order data through the augmented network to measure cost and coverage, and run a geo experiment in a handful of metro areas using expedited carrier capacity to proxy next-day speed. Use synthetic control — not a simple diff-in-diff — to handle the small number of treated geos and the l…