Should We Open a New Distribution Hub? A Full Analytics Framework
Statistics & ExperimentsModel answerLast updated
Design an end-to-end analytical case for a warehouse build-vs-lease decision: demand forecasting, NPV modeling, incrementality experiments, sensitivity analysis, and a stakeholder recommendation.
Opening a New Distribution Hub: Build, Lease, or Wait?
Your team has been asked to evaluate whether the company should open a new distribution hub in an underserved region. Leadership wants a data-driven recommendation before committing capital.
You have access to the following data:
- Daily order volume broken down by metro area
- Current hub locations, their storage capacities, and per-hub variable fulfillment costs
- A delivery-time-vs-distance curve derived from historical shipments
- Two site options: a build-to-own (large upfront capital) and a short-term lease (lower commitment, higher ongoing cost)
Answer all five parts below.
Part 1 — Analysis Plan Outline the full analytical workflow you would follow to arrive at a build / lease / defer recommendation. Cover: the forecasting methodology you would use for regional demand, the service-level target you would optimize against, the network optimization problem formulation (objective function, decision variables, and key constraints), and how you would isolate the value that a new hub adds versus the current network.
Part 2 — Five-Year NPV Model Walk through a back-of-the-envelope NPV calculation over a five-year horizon with a 10% discount rate. State your assumptions explicitly (rerouted volume, cost savings per unit, demand lift from faster delivery, cannibalization, contribution margin, annual growth, ramp curve, fixed site operating cost). Produce a year-by-year cash-flow table and a final NPV for each option. Call out the key insight about which inputs actually swing the decision.
Part 3 — Pre-Commitment Experiment You cannot A/B test a physical building. Describe two complementary approaches that would let you de-risk the decision before signing anything. For each, explain what it measures, how you would validate it, what your primary and guardrail metrics are, and what your stopping rules look like.
Part 4 — Sensitivity Analysis Identify the three input parameters that pose the greatest threat to the recommendation. For each: quantify how much it can move the NPV, explain how you would bound your uncertainty with additional data, and describe how you would present the results to a non-technical audience.
Part 5 — Stakeholder Narrative Sketch the structure of a single-slide recommendation. Include your headline decision, the one-line rationale for the preferred option over the others, and the top two risks with a mitigation for each.
Hints
Hint 1
For the network optimization, think about it as a facility-location MILP: binary open/close decisions for each candidate site, continuous flow variables between sites and metros, and a hard constraint on next-day coverage percentage. The value of a new site is the difference in total cost with and without it in the feasible set.
Hint 2
In the NPV model, separate cost savings (which are high-confidence and drive the bulk of value) from demand lift due to faster delivery (which is uncertain and much smaller). Notice which option's NPV is positive even if you zero out the demand-lift term entirely — that asymmetry should drive your recommendation.
Hint 3
You can't randomize who gets a new warehouse, but you can simulate the counterfactual two ways: replay historical order data through the augmented network to measure cost and coverage, and run a geo experiment in a handful of metro areas using expedited carrier capacity to proxy next-day speed. Use synthetic control — not a simple diff-in-diff — to handle the small number of treated geos and the l…
Model answer
Hard Try it yourself first — then compare your approach, complexity and edge cases.
Solution Walkthrough
The core challenge here is turning a vague capital allocation question into a structured cost-minimization problem, attaching real numbers to it, finding which assumptions could flip the answer, and reducing uncertainty on those assumptions before money is committed.
Part 1 — Analysis Plan
Demand forecasting
Use a hierarchical forecasting model: metro → region → national, with top-down reconciliation. Gradient-boosted trees or ETS with exogenous features (seasonality, promotional calendar, population growth, existing service-level penetration) work well here. Produce quantile forecasts: P50 for cost modeling, P90 at seasonal peak for capacity sizing. Backtest on rolling origins and report MAPE by metro so you know where the forecast is weakest.
Service-level target
A reasonable target is ≥95% of units delivered within the next-day promise. Read this off the delivery-time-vs-distance curve, adjusted for carrier cutoff windows.
Network optimization (MILP facility location)
- Decision variables: binary
y_j ∈ {0,1}for whether candidate sitejis opened; continuousx_ij ≥ 0for units shipped from hubjto metroi. - Objective: minimize
Σ_j (fixed_cost_j × y_j) + Σ_ij (variable_cost_ij × x_ij). - Constraints: demand met for every metro; capacity at each hub not exceeded (sized to P90 peak); at least 95% of total units flow through next-day-feasible hub–metro pairs; labor availability and dock throughput per site.
Run the model with and without the candidate site. The cost and coverage delta is the site's value.
Part 2 — Five-Year NPV Model
Stated assumptions
| Parameter | Value |
|---|---|
| Volume rerouted to new hub | 150k units/day ≈ 54.75M/yr |
| Cost saving per unit (shorter outbound, less linehaul) | $0.80 |
| Demand lift from next-day delivery | +4%, but 50% is cannibalized → net +2% |
| Contribution margin per incremental unit | $6.00 |
| Annual demand growth | 8% |
| Ramp (share of target volume routed each year) | 40 / 75 / 95 / 95 / 95% |
| Fixed operating cost of new site | $15M/yr |
| Discount rate | 10% |
Steady-state annual benefit at year-1 demand
- Cost savings: 54.75M × $0.80 = $43.8M
- Incremental margin: 54.75M × 2% × $6 = $6.6M
- Total gross benefit: ≈ $50.4M/yr
Year-by-year cash flows
| Year | Demand index × ramp | Gross benefit ($M) | Net of $15M opex ($M) | Discount factor | PV ($M) |
|---|---|---|---|---|---|
| 1 | 1.00 × 0.40 | 20.2 | 5.2 | 0.909 | 4.7 |
| 2 | 1.08 × 0.75 | 40.8 | 25.8 | 0.826 | 21.3 |
| 3 | 1.17 × 0.95 | 55.8 | 40.8 | 0.751 | 30.7 |
| 4 | 1.26 × 0.95 | 60.3 | 45.3 | 0.683 | 31.0 |
| 5 | 1.36 × 0.95 | 65.1 | 50.1 | 0.621 | 31.1 |
| Sum | ≈ $118.8M |
NPV by option
- Build: $180M CapEx at t=0, $90M residual value in year 5 (PV ≈ $55.9M). NPV = 118.8 + 55.9 − 180 = −$5.3M
- Lease: $25M fit-out at t=0, $14M/yr lease over five years (PV ≈ $53.1M). NPV = 118.8 − 25 − 53.1 = +$40.7M
- Defer one year: You forfeit roughly year-1 benefit (~$5M PV) and push everything back. Justified only if the information gained could flip the lease decision — as shown below, it cannot.
Key insight: Cost savings account for about 87% of the gross benefit. Zeroing out demand lift entirely still leaves the lease NPV at roughly +$25M. The lease is robust; the build is not, because its NPV is hostage to a five-year residual-value estimate.
Also flag stranded fixed costs at legacy hubs: losing 150k units/day from an existing site leaves its fixed costs underutilized until network growth backfills that volume — typically two to three years at 8% growth.
Part 3 — Pre-Commitment Experiment
A. Network simulation with historical replay (measures cost and coverage)
Replay 12 months of individual order records through the proposed network with the new hub added. Use actual carrier rates, cutoff times, and Q4 peak volumes. Output: cost-per-unit, next-day coverage percentage, and peak utilization. Validate the simulator first by replaying a past hub launch and comparing predictions to actuals; target less than 10% error before trusting any forward-looking output.
B. Geo experiment using expedited carriers (measures demand lift)
In roughly 10 treated metro areas, buy next-day delivery speed today using expedited air or regional-carrier capacity — this mimics what the new hub would enable without building anything. Estimate the counterfactual using synthetic control: a weighted combination of untreated metros fitted on 52 weeks of pre-period data. A simple diff-in-diff is insufficient because the number of treated geos is small and pre-trends matter.
- Primary metric: incremental units per customer in treated metros, net of volume shifts from adjacent metros (this directly measures cannibalization).
- Secondary metrics: conversion rate and 90-day repeat purchase rate.
- Guardrail metrics: on-time delivery rate and cost per unit, each with fixed tolerance thresholds.
- Run for a fixed 8-week window pre-registered for a minimum detectable effect of ~2% lift at 80% power. No early stop on efficacy; early stop only if a guardrail breaches for two consecutive weeks.
- Decision threshold: identify the break-even lift required for the build decision. If the 90% CI sits entirely below it, choose lease without waiting for more data.
- Validity: run placebo tests on untreated metros; confirm they show no effect before trusting the treatment estimates.
Part 4 — Sensitivity Analysis
1. Per-unit cost saving ($0.80) Drives ~87% of total benefit. A ±$0.20 swing moves NPV by roughly ±$26M — large enough to flip the build decision. Bound it with lane-level carrier quotes, labor time studies from comparable sites, and the replay simulator's output.
2. Demand volume: growth rate and ramp shape Dropping from 8% to 3% annual growth with a slower ramp (30/60/85%) cuts cumulative PV by 20–25%. Bound it using P10/P90 forecast ranges and empirical ramp curves from prior hub launches (how long did it actually take previous sites to reach target utilization?).
3. Residual value and CapEx (build) vs. lease rate Build NPV moves nearly dollar-for-dollar with the residual value estimate. A $20M miss in residual value swings NPV by ~$12M in PV terms. Bound it with broker appraisals, industrial-property comparable sales, and firm construction bids rather than internal estimates.
Present results as a tornado chart, one bar per parameter showing the NPV range across plausible bounds. Report the break-even value of each input, not just the swing size — that is what makes the chart actionable for a non-technical audience.
Part 5 — Stakeholder Narrative
Headline recommendation: Lease the [Region] hub now (5-yr NPV ≈ +$41M); retain a build option at the lease renewal break point.
Why lease over build: The lease is NPV-positive even if faster delivery produces zero incremental demand. The build is marginally negative over five years and depends heavily on a residual-value assumption that won't be confirmed until year five. A ten-year horizon would likely favor build — but that decision can be revisited with more data.
Risk 1 — Cost savings are lower than modeled. At $0.60/unit instead of $0.80, lease NPV drops to roughly +$10M, still positive. Mitigation: lock in carrier rate agreements and run the replay simulator on Q4 peak data before signing the lease.
Risk 2 — Legacy hub fixed costs become stranded. If volume rerouted away from an existing hub isn't replaced by network growth for two or more years, that site's economics deteriorate. Mitigation: model legacy hub utilization explicitly and plan either a volume-shift schedule or a partial capacity release.